Sprint 1 requirements traceability

Document information Details
Project Sport Analytics Tool
Milestone Sprint 1
Related issue #70
Purpose Trace the course-wide and Sport Analytics requirements to implementation, issues, Pull Requests and repository evidence
Status Sprint 1 close-out record

1. Purpose

This document records the Sprint 1 requirements traceability baseline for the Sport Analytics Tool.

It supplements the detailed project backlog by mapping the externally defined project requirements to:

  • their Sprint 1 implementation status;
  • relevant Gitea issues;
  • representative Pull Requests;
  • implementation or documentation evidence; and
  • known incomplete work.

The status recorded here describes the state reached during Sprint 1. It does not imply that every Basic, Intermediate or Advanced project requirement is complete.

Gitea remains authoritative for current issue and Pull Request state.

2. Status definitions

Status Meaning
Implemented The requirement has a working Sprint 1 implementation and supporting evidence.
Implemented foundation The required foundation exists, while later hardening or extension remains planned.
Partial A meaningful portion is implemented, but part of the requirement remains incomplete.
Planned The requirement is intentionally scheduled for a later sprint.

3. Course-wide requirements

Requirement Sprint 1 status Implementation and evidence Issues / representative PRs Remaining work
Git-based version control Implemented Repository uses Gitea with documented GitHub Flow adapted for Gitea, issue-linked branches, Conventional Commits, Pull Request review and protected main practices. See docs/git-methodology.md. #2, #7, #8; PR #3, PR #9 Continue applying the methodology consistently through later sprints.
Responsiveness and accessibility Implemented foundation Responsive public layouts, accessible component conventions and browser-based public journey validation are present. See docs/design/frontend-component-baseline.md, docs/design/information-architecture-and-wireframes.md and evidence/user-testing/2026-08-23-issue-199-public-data-journeys.md. #56, #57, #199; PR #219, PR #224, PR #228 Continue accessibility and responsive testing as additional features are added.
CI/CD Implemented foundation Automated quality checks, Azure frontend/backend deployment workflows and Cloudflare Pages documentation deployment are configured. Azure monorepo workflow paths were repaired during Sprint 1. #10, #15, #17, #29, #69; PR #23, PR #41, PR #178 Continue deployment smoke verification and production hardening.
Separate frontend and backend applications Implemented React/Vite frontend and Express/TypeScript backend are maintained separately under apps/frontend and apps/backend, with shared contracts isolated in packages/contracts. See docs/architecture/system-architecture.md. #38; PR #42 Maintain the boundary as the system grows.
Team-designed handwritten API Implemented All application HTTP endpoints are implemented through the Express backend under /api/v1; generated Supabase Data API endpoints are not used. OpenAPI and shared API conventions are version controlled. #58, #59; PR #94, PR #97 Expand the same API conventions to later-tier endpoints.
Authentication and security Implemented foundation Supabase Auth provides managed identity and Google OAuth. The backend verifies identities and owns application roles and competition scopes. Sign-in, account lifecycle, password-recovery ownership and self-service deletion are documented and implemented. #14, #39, #44, #65, #66; PR #34, PR #100, PR #123, PR #160, PR #177, PR #186 Continue security hardening and later review/publication workflows.
Relevant external API integration Implemented Open-Meteo is called server-side through the handwritten GET /api/v1/weather endpoint with validation, timeout handling and safe upstream-error mapping. See docs/api/weather.md and evidence/decisions/ADR-008-external-weather-api-integration.md. #174; PR #210 Fixture-to-venue coordinate lookup and caching remain deferred.
Public documentation website Implemented MkDocs documentation is version controlled and deployed publicly through Cloudflare Pages at https://sports-analytics-tool.pages.dev. #11, #29; PR #22, PR #41 Maintain the site as implementation changes.

4. Sport Analytics Basic requirements

4.1 Event-derived statistics and correction model

Requirement Sprint 1 status Implementation and evidence Issues / representative PRs Remaining work
Platform data is built from ordered fixture events rather than manually entered totals Implemented Cricket deliveries are represented as ordered event data in PostgreSQL and exposed through the API. The event model is documented in docs/database/schema.md. #27, #67; PR #76, PR #79, PR #159 Continue extending event handling for later ingestion modes.
Published fixture statistics are derived from event data Implemented Fixture totals and participant batting/bowling statistics are derived from accepted deliveries. See docs/statistics/fixture-statistics.md, docs/api/event-statistic-mapping.md and evidence/validation/issue-52-fixture-statistics.md. #52; PR #133 Season, competition and career aggregates are later-tier requirements.
Correcting an event updates every dependent statistic without manual re-entry Partial The schema preserves event provenance and the architecture defines correction history and recomputation, but the authorised correction workflow and dependent recomputation are not yet implemented. #27, #61; later correction work remains planned Implement authorised event corrections, retained history and targeted recomputation.
Statistics are traceable to source events Implemented foundation Fixture statistics are calculated from stored delivery events and submission provenance is retained. #51, #52; PR #134, PR #133 Expand provenance presentation when correction/version workflows are introduced.

4.2 Submission, validation and provenance

Requirement Sprint 1 status Implementation and evidence Issues / representative PRs Remaining work
Only approved submitters may submit data Implemented Backend authorisation requires the submitter role and approved application state. #43, #44, #45, #51; PR #123, PR #157, PR #134 Maintain deny-by-default authorisation for later submission paths.
Submitters operate within a defined competition scope Implemented Competition grants are server-owned and checked before submission acceptance. #43, #44, #45, #51; PR #137, PR #157, PR #134 Extend scope checks to batch and correction workflows.
Submission is checked against the event schema before acceptance Implemented Shared submission contracts and cricket-domain validation reject structurally or semantically invalid deliveries. #49, #50, #51; PR #142, PR #147, PR #134 Extend the same validation to file and batch ingestion.
Rejected submissions explain what is wrong Implemented Structured validation errors identify invalid fields/events instead of failing silently. See docs/api/submissions.md and evidence/validation/issue-51-direct-event-submission.md. #50, #51; PR #147, PR #134 Maintain actionable errors for future batch-level rejection reports.
Submission provenance identifies who supplied the events Implemented Accepted submissions retain application-user, competition and source provenance. #51; PR #134 Extend provenance to corrections, reviews and releases.
Direct submission path Implemented Approved submitters can submit ordered delivery events through POST /api/v1/submissions. #51, #53; PR #134, PR #148 Continue usability improvements as required.
File-based submission Planned The Basic requirement permits submission either by file upload or directly to the platform. Sprint 1 implements the direct JSON submission path, so file upload is an additional planned ingestion path rather than a blocker to that requirement. Future submission work If retained in the backlog, implement file upload using the same event schema, validation and provenance rules.

4.3 Public API and data access

Requirement Sprint 1 status Implementation and evidence Issues / representative PRs Remaining work
API is a primary product interface Implemented Public and protected application functionality is exposed through the handwritten Express API and documented in OpenAPI. #47, #58, #59; PR #95, PR #94, PR #97 Continue treating API contracts as first-class product behaviour.
Consumers can read fixtures Implemented Anonymous competition, season and fixture resources are available through /api/v1. #47; PR #95 Continue enriching related-record summaries where useful.
Consumers can read ordered fixture events Implemented Accepted deliveries are exposed in deterministic occurrence order. #67; PR #159 Later live/change-feed requirements remain separate.
Consumers can read derived fixture statistics Implemented Fixture and participant statistics are available through public API endpoints. #52; PR #133 Wider aggregates are planned for Sprint 2.
Collection requests support documented filtering Implemented Public-read endpoints expose documented query filters and readable filtering behaviour. See docs/api/public-read.md. #47, #194; PR #95, PR #211 Expand filtering with later resources where required.
Large collections can be paged Implemented Public collection contracts use documented cursor pagination and deterministic ordering. #47, #58; PR #95 Continue contract testing as collections grow.
Identifiers are stable Implemented foundation Shared API conventions define stable opaque non-recycled identifiers, and public resources resolve through persistent database identifiers. #58 Preserve identifiers across later release/version work.
Analysts can export a filtered data slice as a file Partial Export behaviour is documented in the architecture and roadmap but a filtered dataset export endpoint/file workflow is not implemented in the Sprint 1 product. Planned Basic follow-up Implement filtered export before declaring the full Basic API requirement complete.

5. Sprint 1 requirement review

The complete Basic, Intermediate and Advanced interpretation was reviewed with the stakeholder on 18 August 2026.

The stakeholder confirmed:

  • the team's interpretation of the Basic requirements;
  • the planned Sprint 2 timing for Intermediate requirements;
  • the planned Sprint 3 timing for Advanced requirements; and
  • the continued applicability of the course-wide requirements.

No requirement changes were requested during that review.

The stakeholder additionally requested that the full required T20 dataset be available by the next meeting. The full import was subsequently recorded in evidence/validation/issue-175-dataset-import.md. That request changed execution priority, not the project requirement set.

See evidence/sprints/sprint-1/2026-08-18-stakeholder-meeting.md.

6. Material requirement and architecture changes

Date Source Decision / change Affected work
5 Aug 2026 Lecturer/client written clarification retained in evidence/decisions/2026-08-05-lecturer-ruling-supabase.md and ADR-003 Supabase may be used as hosted PostgreSQL provided generated Data API endpoints are not used. The team retained a handwritten Express API as the only application-data HTTP boundary. Database hosting, backend connection, architecture, API boundary and compliance documentation.
6 Aug 2026 ADR-004, superseding ADR-002 Authentication changed from the initial Firebase proof to Supabase Auth with Google OAuth. Authentication continues to establish identity only; application roles remain backend-owned. Frontend auth client, backend token verification, environment variables, authentication tests and security documentation.
12 Aug 2026 ADR-005 The PostgreSQL database moved to a Supabase project with sufficient storage because the original project could not accommodate the intended corpus. The application remained provider-neutral through DATABASE_URL and committed migrations. Database configuration, developer environment, Azure configuration, ingestion planning and storage benchmarking.
18 Aug 2026 Sprint 1 stakeholder requirements review The stakeholder confirmed the team's Basic, Intermediate and Advanced interpretations and sprint timing with no requested requirement changes. Loading the complete T20 corpus became the immediate execution priority for the next meeting. Sprint planning and data-ingestion priority; no change to the requirement baseline.
19 Aug 2026 ADR-007 / issue #191 Public information architecture moved from technical-ID-oriented browsing toward readable cricket names, embedded related records and key information within three purposeful interactions. Public API enrichment and frontend issues #192–#199.
20 Aug 2026 ADR-008 Open-Meteo was selected as the course-required runtime external API integration and isolated behind GET /api/v1/weather. Backend weather service/controller/router, tests, OpenAPI and public documentation.
21 Aug 2026 ADR-009 to ADR-012 / issue #55 Later-tier cache, background-job, object-storage and live-ingestion designs were recorded with explicit adoption gates rather than being added prematurely to the Sprint 1 runtime. Sprint 2/Sprint 3 architecture and future implementation planning; no Sprint 1 runtime services were added.

7. Known Sprint 1 limitations relevant to the requirements

The following gaps are intentionally recorded rather than presented as complete:

  • authorised event correction and dependent-statistic recomputation are not yet implemented;
  • the direct JSON submission path is implemented; a separate file-upload ingestion path remains planned but is not required where direct submission satisfies the Basic ingestion alternative;
  • filtered dataset export is not yet implemented;
  • season, competition and career aggregates belong to later-tier work;
  • Open-Meteo currently accepts raw latitude and longitude rather than resolving a fixture venue automatically;
  • weather responses are not cached;
  • later review/publication, batch-ingestion, dataset-release and API-consumer controls remain planned for Sprint 2;
  • the advanced custom-statistic, live-ingestion, temporal-query and change-feed capabilities remain planned for Sprint 3.

These limitations are consistent with the Sprint 1 goal of establishing a working Basic vertical slice and strong project foundations rather than claiming later-tier completion.

Detailed Sprint 1 work-to-issue mapping is maintained in:

  • docs/planning/project-backlog.md

Architecture and implementation state are maintained in:

  • docs/architecture/system-architecture.md
  • docs/development/technology-stack.md
  • docs/api/overview.md
  • docs/development/testing.md

Sprint 1 process evidence includes:

  • evidence/sprints/sprint-1/2026-08-04-stakeholder-meeting.md
  • evidence/sprints/sprint-1/2026-08-06-planning.md
  • evidence/sprints/sprint-1/2026-08-06-standup.md
  • evidence/sprints/sprint-1/2026-08-11-stakeholder-meeting.md
  • evidence/sprints/sprint-1/2026-08-13-standup.md
  • evidence/sprints/sprint-1/2026-08-18-stakeholder-meeting.md
  • evidence/sprints/sprint-1/2026-08-20-standup.md

AI Declaration

The preceding document was planned, generated, reviewed and edited with the assistance of ChatGPT-Web[GPT-5.6 Sol].