Related issues: #577, #613 Evidence status: Pre-finalisation — actual evidence mapped through 28 September 2026

State refresh: 28 September 2026 — only #612 and #613 remain open in the Sprint 3 milestone.

This page converts the Sprint 3 planning baseline into marker-facing actual evidence. It does not award a mark or infer completion from an issue being closed. Where the current evidence is incomplete, that limitation is stated explicitly.

The historical planned mapping remains in evidence/sprints/sprint-3/2026-09-15-planning.md. The Sprint 3 close-out record is evidence/sprints/sprint-3/2026-09-28-sprint-3-close-out.md.

Current Milestone State

At the latest 28 September milestone refresh, only two Sprint 3 issues remain open:

  • 612 — selected Advanced API consumer user feedback; and

  • 613 — Sprint 3 close-out.

Issues #604, #776 and #779 have closed since the first pre-finalisation draft. Their closed state is recorded here, but the final close-out still links their actual retained evidence rather than treating issue closure alone as proof of a passing test or defect resolution.

Everything below is interpreted against that visible state. #612 remains incomplete until its final user-feedback outcome is recorded.

Sprint 3 Rubric — Planned vs Actual Evidence

Rubric category Weight Actual Sprint 3 evidence Current evidence state Finalisation action
User Feedback 10% Formal task-based process under #600; retained Sprint 3 session evidence; #601–#607 now closed in the milestone; #605/#778 records a not-accepted/deferred result; #612 remains open One user-feedback gate remains open (#612). #604 is now closed but its exact final result still needs reconciliation; closure is not treated as PASS Reconcile the latest summary, exact #604 result and final #612 outcome
Automated Testing 10% #578 repository-wide coverage; regression/unit/API/database/worker/frontend suites; Playwright; OpenAPI/deployment tests; #598 acceptance Strong automated evidence exists, but #598 final PASS/FAIL is not yet imported into this pre-finalisation record Add final #598 result and current CI links
Feature Implementation 20% Basic/Intermediate hardening, new-fixture/onboarding, multi-season implementation, corrections/provenance, statistics/frontend improvements The previously open high-priority #779 defect is now closed; no remaining open milestone item is an implementation defect, while #612 remains a user-validation gate Link #779 final fix/verification evidence and keep any retained limitations explicit
API Implementation 20% Public OpenAPI specification and Explorer (#658–#661), consumer controls, dataset/API work, selected Advanced API issues #608–#611 #776 is now closed; #612 still has not completed representative-user validation of the selected Advanced group Link #776 final evidence and record #612 final outcome
Performance 5% #599 representative 300-fixture/72,000-event local revalidation; prior deployed season-scale acceptance; later deployed API response-time follow-up #765 Local targets passed/no regression; deployed response-time evidence must be linked from current main; #599 retains explicit limitations Link #765 final evidence; keep release-generation variance and test-isolation limitation visible
Improvement 5% Sprint 2 stakeholder feedback converted into #579–#582/#513; #647 closure-gate refinement; API Explorer and UX improvements; Sprint 3 stakeholder review Evidence exists of feedback-driven and process-driven change Link exact issue/PRs used in final close-out
Documentation 15% #577 planning; #579 DB docs; #578 coverage docs; API/OpenAPI docs; deployment/testing docs; Sprint evidence; #613 close-out and this traceability page Substantive documentation trail exists Final link audit and strict docs build
Project Methodology 15% Scrumban/progressive refinement; issue tracker; stand-ups; stakeholder interaction; formal user-testing gates; acceptance/performance gates; explicit carry-forward Methodology is evidenced across the sprint and unfinished work is visible Record peer review and final milestone/tag evidence

User-Feedback Gate Traceability

The consolidated source of truth is evidence/user-testing/sprint-3/sprint-3-user-testing-summary.md.

Gate User goal Current close-out treatment
#601 Navigation, authentication and overall frontend flow Accepted with documented limitations in retained summary
#602 Public statistics and fixture analytics Closed in current Gitea milestone state; final retained result/retest must be reconciled from current main
#603 New fixture submission and reviewer onboarding Closed in current Gitea milestone state; final retained result must be reconciled from current main
#604 Season and multi-season back-catalogue ingestion Closed in current Gitea milestone state; exact final retained result/retest still to be reconciled from current main
#605 Corrections, stable identity and provenance Closed not accepted; findings deferred in #778; exact finding rows must be copied from final retained evidence
#606 Versioned dataset release and reproducibility Accepted in retained summary
#607 API consumer keys, quotas and rate limits Accepted with documented limitations in retained summary
#612 Selected Advanced API consumer capabilities OPEN — incomplete

Closing an issue is not treated as a synonym for a passing user result.

Automated Coverage Traceability — #578

Retained baseline:

Metric Covered / total Percentage
Lines 5,466 / 8,566 63.81%
Statements 5,628 / 8,999 62.54%
Functions 1,385 / 2,013 68.80%
Branches 3,790 / 6,627 57.19%

The repository aggregation is counter-based across frontend, backend, worker, contracts and batch-processing; unimported production source remains in the denominator. Temporary pass/fail line thresholds were used to prove enforcement and were not adopted as an invented course threshold.

Evidence: evidence/validation/issue-578-repository-code-coverage.md.

Intermediate Acceptance Traceability — #598

Explicit result in this pre-finalisation record: PENDING FINAL IMPORT.

598 is closed in the current milestone state, but the repository snapshot used for this draft does

not contain the authoritative final closure record needed to state PASS or FAIL responsibly.

The final #613 pass must insert the exact result and link its deployed evidence. A closed issue alone is not used as proof of acceptance.

Performance Traceability — #599 / #765

599 measured a deterministic 300-fixture / 72,000-event corpus locally and reports that all targets

set before measurement passed with no regression against the comparable prior local evidence.

Examples from the least favourable of the three primary local API runs:

Operation P95 Target
Public fixture page 15.3 ms 500 ms
Fixture event page 33.1 ms 750 ms
Fixture statistics 43.9 ms 1,500 ms
Participant aggregate 259.4 ms 1,500 ms
CSV event export 69.9 ms 1,000 ms

These are local results, not deployed response times.

The same report records important non-pass-style findings:

  • dataset release generation ranged from 4.3 s to 16.2 s for identical output and remains too variable for a stable target;
  • the query-plan check must be isolated from the shared database suite; and
  • horizontal scaling was not tested even though the original single-replica rationale may have changed after shared rate-limit state.

A later deployed-response-time follow-up exists under #765. Add its merged evidence link and final figures during #613 finalisation.

API / Advanced Traceability

Public API / OpenAPI experience

Sprint 3 added the externally usable API documentation path through #658–#661:

  • anonymous OpenAPI specification exposure;
  • hardened contract metadata/linting;
  • public Swagger API Explorer; and
  • product navigation/integration plus deployment/browser verification.

Selected Advanced work

The sprint intentionally selected only four Advanced API issues rather than the entire Advanced tier.

Issue Capability Actual treatment
#608 API deprecation lifecycle Closed in current milestone state; link final evidence before #613 closes
#609 OpenAPI / API contract enforcement Closed; contract/deployment tests provide supporting evidence
#610 Per-consumer API usage Core issue closed; administrator visibility follow-up #776 is now closed; link final evidence before #613 closes
#611 Advanced aggregate-query support Closed in current milestone state; link final evidence before #613 closes
#612 Representative user validation Open — selected Advanced group is not yet fully user-validated

No claim is made that unselected Advanced project-brief requirements were completed.

Stakeholder Feedback Traceability

The 22–24 September asynchronous stakeholder review asked whether any important cricket/analytics/API capability was missing and what one item should be prioritised before Sprint 3 closed.

The stakeholder reported no important missing capability or major pre-close change from what they had seen, but raised two minor UX concerns:

  • page-position/pagination clarity in seasons/players views; and
  • asynchronous API Explorer rendering without a visible loading indicator/spinner.

Evidence is retained under evidence/sprints/sprint-3/2026-09-22 Asynch Stakeholder meeting/ and summarised in evidence/sprints/sprint-3/2026-09-28-stakeholder-review.md.

Known Open Work / Limitations

Item Current close-out treatment
#612 Open. Selected Advanced user-feedback gate is the only non-close-out Sprint 3 issue still open
#604 Now closed; exact final user-testing outcome still needs reconciliation from retained evidence
#776 Now closed; final implementation/verification evidence should be linked
#779 Now closed; final defect-fix/retest evidence should be linked
#605/#778 Closed but not accepted; findings are deferred, so closure is not presented as a pass
#599 release-generation variance Performance evidence remains variable for this workload
#598 final result Must still be imported explicitly before milestone closure

Milestone / Tag Evidence

Pending finalisation. The final Sprint 3 tag and commit SHA must be added only after the close-out has been reconciled with current main and reviewed by another team member.

Finalisation Checklist

  • [ ] Reconcile latest #601–#607/#612 summary with this page, including the exact final #604 result.
  • [ ] Add exact #598 PASS/FAIL and deployed acceptance link.
  • [ ] Add merged #765 deployed response-time evidence and final figures.
  • [x] Refresh milestone status: #604 / #776 / #779 are now closed; only #612 and #613 remain open.
  • [ ] Link final closure/verification evidence for #604 / #776 / #779.
  • [ ] Record final #612 result or explicit carry-forward.
  • [ ] Link final issue/PR evidence for #608–#611 individually.
  • [ ] Run strict documentation build and link/check all marker-facing evidence.
  • [ ] Obtain another team member's review of the close-out/traceability.
  • [ ] Add final Sprint 3 tag name and commit SHA.

AI Declaration